What is Glitre Nett up to?

2 strategic moves read from public sources, up to 30 Sept 2026.

Advancing Kystlinja development Preparing Kaggefoss package

Advancing Kystlinja development

Glitre Nett appears to be moving forward with a larger regional network project in Agder, extending the existing Kystlinja corridor from Kristiansand toward Kvinesdal. The effort includes an impact assessment and new concession applications for additional sections of the line.

Public filings and regulator notices show that the company has submitted a concession request for rebuilding the Kulia‑Fiskå 110 kV line, that NVE has opened a hearing on a new 110/132 kV line from Leire to Kanten/Hjorteland, and that earlier segments of the roughly 80 km corridor already hold concessions and have begun construction. Press coverage also notes ongoing discussions about possible route alternatives, confirming the project’s active status in the authority process.

  1. Glitre Nett submitted an application for a construction concession to rebuild the Kulia‑Fiskå 110 kV transmission line.

    einnsyn.no

  2. Industry press covered Glitre Nett’s concession filing for the last part of the Kystlinja and highlighted discussion of a possible route alternative along the E39, confirming the project is in an active regulatory process.

    energiteknikk.net

  3. Glitre Nett reported that NVE has started processing the concession application for the final segment of the Kystlinja from Leire in Søgne to Kanten at the Mandalselva, describing the line as an approximately 80 km connection from Kristiansand to Kvinesdal and noting that earlier sections already have concessions and construction has started on Kulia‑Leire.

    kommunikasjon.ntb.no

  4. NVE opened a hearing for Glitre Nett’s concession application and impact assessment for a new 110(132) kV line from Leire in Kristiansand to Kanten/Hjorteland in Lindesnes.

    webfileservice.nve.no

Preparing Kaggefoss package

Glitre Nett appears to be moving the Kaggefoss area from the application stage toward a coordinated network‑expansion effort that includes a new coupling station, the rebuilding of the existing substation and several line upgrades.

Public filings show that NVE has granted Glitre Nett permission for the Kaggefoss coupling station, the transformation of the existing Kaggefoss substation, a 132 kV underground cable, and the reconstruction of several transmission lines associated with the project.

  1. NVE gave Glitre Nett permission to rebuild the Kaggefoss transformer station.

    webfileservice.nve.no

  2. NVE described Glitre Nett's approved scope as a new Kaggefoss coupling station, a 132 kV underground cable to the existing Kaggefoss transformer station, reconstruction of the transformer station and rerouting of several transmission lines.

    webfileservice.nve.no

  3. NVE granted Glitre Nett permission to construct the 132 kV Kaggefoss–Holgersmoen transmission line, reinforcing the picture of a comprehensive network reinforcement around Kaggefoss.

    webfileservice.nve.no

  4. NVE granted Glitre Nett permission to construct the 132 kV Kaggefoss–Gravfoss transmission line, showing that the line component of the package is also consented.

    webfileservice.nve.no

  5. NVE granted Glitre Nett permission to build the Kaggefoss coupling station.

    webfileservice.nve.no

  6. NVE granted Glitre Nett and Å Energi permission for several electric facilities at Kaggefoss, moving the project from the application and regulatory dialogue to an approved construction package.

    nve.no

Paldo wrote this page from the public sources linked above. What a company appears to intend is our reading and may be wrong. If something is out of date, tell us.