What is Bulk Infrastructure up to?

2 strategic moves read from public sources, up to 30 Oct 2026.

Preparing data center in Arendal Expanding capacity at N01

Preparing data center in Arendal

Bulk Infrastructure appears to be moving forward with a large data‑center project at the Longum Nord site in Arendal. The plan includes securing substantial power capacity and formalizing a dedicated business unit for data‑infrastructure.

Public records show that the municipality approved the sale of the Longum Nord parcel to Bulk, that the company has applied for 150 MW of electricity for the site, that zoning changes were filed to permit data‑center use, and that a dedicated Bulk Data Centers Arendal registration exists. Media reports also note a purchase price of about 600 million kr.

  1. Dagsavisen reports that Arendal approved the sale of the Longum Nord parcel to Bulk Infrastructure for a data‑center development.

    dagsavisen.no

  2. TU reports that Bulk applied for 150 MW of power for the site outside Arendal, linking the request to the data‑center project.

    tu.no

  3. Arendal municipality scheduled a site inspection related to the zoning amendment for Eyde Material Park, indicating the planning process is active.

    arendal.kommune.no

  4. Arendal municipality posted a zoning amendment for Eyde Material Park, Longum Nord, opening two zones for data‑center purposes.

    arendal.kommune.no

  5. Finansavisen notes that Bulk purchased a parcel for approximately 600 million kr.

    finansavisen.no

  6. The business register shows a dedicated Bulk Data Centers Arendal entity with an industry code for data‑infrastructure, processing and storage.

    virksomhet.brreg.no

Expanding capacity at N01

Bulk Infrastructure appears to be advancing a financed expansion of capacity at the N01 site covering Vennesla and Kristiansand.

Public indications include progress on construction, regulatory approvals, land preparation, and recent senior unsecured bond issuances that provide capital for the development.

  1. The Q3 report dated 2026-10-22 states that construction of new capacity at N01 outside Kristiansand is proceeding according to plan and that planning for additional builds and site preparation has begun.

    bulkinfrastructure.com

  2. An NRK report on 2026-10-16 notes that Bulk will expand the data centre in Vennesla into Kristiansand, with land clearing and a new transformer station, and that 600 MW of a 900 MW capacity is reserved for Bulk.

    nrk.no

  3. Correspondence dated 2026-09-29 about the approval of the cost‑benefit analysis DCM401 shows Bulk handling a regulatory approval process for a specific data‑centre‑related measure.

    einnsyn.no

  4. Arctic Securities listed a senior unsecured bond of NOK 1 billion for Bulk Infrastructure in September 2026, indicating access to capital for further digital infrastructure development.

    arctic.com

  5. Bulk announced on 2026-08-28 that it had completed a new senior unsecured bond issuance, reinforcing its financing for ongoing digital infrastructure projects.

    bulkinfrastructure.com

Paldo wrote this page from the public sources linked above. What a company appears to intend is our reading and may be wrong. If something is out of date, tell us.